Tenders must be judged only on the criteria that bidders were told about before they tendered. The Public Procurement Authority's chief executive, Frank Mante, made the point to heads of public bodies and members of tender committees at the 12th Public Procurement Forum in Accra on 9 November 2026, as reported by Graphic Online.
According to the report, Mr Mante said that:
- evaluation panels must not introduce assessment criteria that were not disclosed to bidders before tendering;
- Entity Tender Committees and the Central and Regional Tender Review Committees have no authority to add evaluation criteria, or to change evaluation reports, outside the procedures the law sets out;
- a committee may approve an evaluation report, reject it if it does not meet the disclosed criteria, or ask for the action the law requires;
- chief executives remain accountable for a breach even when a higher authority has approved the transaction.
What bidders can do
Read the evaluation criteria in the tender documents before you prepare your bid: they are what your bid should be judged on. If a criterion is unclear, ask the buyer for clarification within the time the documents allow.
If you believe a public body has not followed the rules, the Public Procurement Act gives suppliers, contractors and consultants a right to complain (section 78). While the contract has not yet entered into force, a complaint goes first, in writing, to the head of the procurement entity (section 79). After that, or if the head does not decide in time, the complainant can ask the PPA for an administrative review (section 80). The Act sets short time limits, counted from when you knew or should have known about the problem, so act quickly. Read sections 78 to 80 of the Act as amended, or ask the PPA, before you file.
In April 2026 the PPA set up a Complaints Review Committee of its Board to deal with complaints from suppliers, contractors and consultants. The Board's chair, Basil Ahiable, encouraged them to report problems to the Authority, and also warned that a supplier who files a complaint without grounds may be sanctioned.
More on the steps of a public tender: How public tenders work in Ghana and What a tender bid needs.
Sources
- PPA warns CEOs over procurement breaches and irregularities in government contracts, Graphic Online, 9 November 2026
- PPA inaugurates Complaints Review Committee, Public Procurement Authority, 10 April 2026
- Public Procurement Act, 2003 (Act 663), published by the Public Procurement Authority
- The Public Procurement Act and its 2016 amendment (Act 914), Public Procurement Authority
News for suppliers, as reported by the sources above on the date shown. It is not legal advice; confirm how it applies to your bid with the Public Procurement Authority or the organisation that issued the tender.